For well and septic placement on a Kenai Peninsula lot, the controlling number is 100 feet: Alaska DEC requires the well to sit at least 100 feet from the septic tank, the drainfield, and any sewer line outside the house, and the tank and drainfield to sit at least 100 feet from any lake, stream, spring, or slough. Your neighbors' wells and septic systems count too. Place the well and septic first, then fit the house and driveway into what is left.
Getting the order backward is how people end up with a house in the only spot that would have taken a drainfield. Our post on the order of site work for a new home covers the full build sequence. This one is about the layout.
DEC separation distances for wells and septic
DEC moved its separation distances into separate sections when it rewrote 18 AAC 72 in October 2023. The well distances are in 18 AAC 72.100, and the septic distances are in 18 AAC 72.520. Distances are measured edge to edge, from the nearest edge of one thing to the nearest edge of the other.
| From | To | Minimum distance |
|---|---|---|
| Private well | Septic tank, holding tank, drainfield, lift station | 100 feet |
| Private well | Sewer lines, cleanouts, and manholes | 100 feet |
| Private well | Outhouse (pit privy) | 100 feet |
| Private well | Private sewer line or sump inside a building | 25 feet |
| Private well | Fuel tank or fuel line (propane, natural gas, and small above-ground tanks totaling 500 gallons or less are exempt) | 25 feet |
| Private well | Discharge area for water softener backwash or reverse osmosis reject water | 25 feet |
| Septic tank or drainfield | Lake, river, stream, spring, or slough (mean annual high water) | 100 feet |
| Drainfield | Slope steeper than 25 percent that drops more than 10 feet | 50 feet |
| Septic tank | Drainfield | 5 feet |
| Drainfield | Another drainfield | 6 feet, or twice the depth of the drain rock if greater |
| Water line | Septic tank, holding tank, lift station, or drainfield | 5 feet |
| Water line | Private sewer line | 12 inches side to side; at crossings, 12 inches vertical with the sewer below |
| Water line | Fuel tank or fuel line | 10 feet |
| Public water system well | Septic systems, drainfields, lift stations, sewer lines | 200 feet |
| Public water system well | Private sewer service lines | 100 feet |
DEC can require greater distances where soils, groundwater, or past experience call for it, and it can approve lesser distances only through a waiver. The vertical rules matter as much as the horizontal ones: a conventional drainfield needs 4 feet of soil between the bottom of the drain rock and the high water table. Our perc test guide covers that part.
The public water system rows apply when a well on or near your lot is a public water system under DEC's drinking water rules, which can include a subdivision water system or a well serving a lodge, campground, or business. Those distances come from DEC's drinking water rules (18 AAC 80.020), and they are double the private ones. If you are building next to a campground or a commercial well, ask DEC before you set your drainfield.
Your neighbors' wells set your lines too
DEC's distances do not mention property lines. They protect water sources, and a neighbor's well is a water source. If their well sits 15 feet from your shared line, its 100 foot circle reaches 85 feet into your lot. No part of your tank, drainfield, or outdoor sewer line can go inside it.
The same rule runs the other way. You cannot drill your new well within 100 feet of a neighbor's existing drainfield. On older subdivisions with small lots, the first owners to build often took the easy spots, and the last lot gets what is left.
Find the wells before you design anything:
- Search DNR's Well Log Tracking System (WELTS). You can search by subdivision name, parcel description, township and range, or map. Drillers have to file logs within 45 days of finishing a well, but DNR says its data are provisional, and older wells may have no log at all.
- Walk the lot lines and look for well casings, pump house roofs, and cleanout or monitor pipes sticking out of the ground.
- Ask the neighbors. Most people know where their well and septic are, and the conversation saves a survey crew hours.
- Ask DEC for records on your parcel and the adjoining ones. DEC charges $25 to search and copy records by legal description.
A worked layout on a 1 acre lot
Take a 1 acre lot, 165 feet wide and 264 feet deep (43,560 square feet), with the road on the short side. The neighbor to the east has a well 15 feet off the line and 60 feet back from the road.
- The neighbor's circle reaches 85 feet into your lot and covers the east half of your frontage for roughly the first 160 feet back from the road. Your septic cannot go there.
- Put your well near the road, on the west side. Its own 100 foot circle covers the front of the lot, which is where the driveway and the house front go anyway.
- Put the tank and drainfield at the back. From about 170 feet back to the rear line leaves a strip roughly 94 feet deep and 165 feet wide, which is plenty for a conventional field for a 3 or 4 bedroom house in decent soil.
- Put the house in the middle, with the sewer line leaving the back wall. Check that the line stays 100 feet from your well along its whole run, and that the plumbing inside the house stays 25 feet from it.
- Run the water line from the well to the front of the house, at least 5 feet from the tank and drainfield and 12 inches from the sewer line where they cross. Our post on how deep to bury a water line covers depth and insulation.
Move the neighbor's well 60 feet further back, or add a creek at the rear of the lot, and this layout stops working. That is why you draw the circles before you buy, if you can.
Leave room for a second drainfield
When an engineer submits an alternative system to DEC for approval, the plans have to show an area reserved for a replacement field. Conventional systems do not carry that rule, but reserve ground is still smart planning. Every drainfield eventually wears out, and the replacement has to meet the same distances as the original. If the house, the shop, and the well have used up the rest of the lot, a failed field can turn into an engineered system or a holding tank.
Mark the reserve area on your site plan and keep buildings, driveways, and parking off it.
Fit the house and driveway around the septic
Once the well and septic are placed, the rest follows:
- Driveway. Keep it clear of the tank and the field. Vehicle weight crushes drain pipe and compacts soil. If the driveway enters a borough road, the borough's driveway permit calls for a culvert at least 15 inches by 30 feet. See our driveway permit guide.
- Pumper access. The pump truck has to reach the tank cleanout. A tank 150 feet from any drivable surface means a longer hose and a bigger bill every few years.
- Plat setbacks. Many borough subdivision plats carry a building setback along road rights-of-way. Read your plat notes before you set the house line.
- Inside the City of Kenai. Kenai requires a utility letter before it issues a certificate of occupancy for a home on a well or septic instead of city service.
- Fall of the land. A gravity sewer line runs downhill from the house to the tank at a 2 percent minimum slope. If the drainfield ground sits above the house, you are paying for a lift pump and an alarm circuit.
Lay out your lot before you build
MNA Construction digs the test holes, clears and grades the building site, and builds the septic system, driveway, and pad in an order that keeps the distances intact. We are glad to walk a lot with your survey and talk through where things fit before you commit to a house plan. Start with a free estimate request, or see our site preparation and septic system services.
Common questions
- How far does a well have to be from a septic system in Alaska?
- At least 100 feet from the septic tank, the drainfield, lift stations, and sewer lines outside the building, measured edge to edge under 18 AAC 72.100. A well serving a public water system needs 200 feet. DEC can require more where soils or groundwater call for it.
- Can my septic system be closer than 100 feet to my neighbor's well?
- Not without a DEC waiver. The 100 foot distance protects any private water source, including one on the next lot. If a neighbor's well sits near the property line, its circle can take a large part of your lot out of play for a tank or drainfield.
- How do I find out where neighboring wells are on the Kenai Peninsula?
- Start with DNR's Well Log Tracking System (WELTS), which you can search by subdivision, parcel, township and range, or map. DNR notes the data are provisional and older wells may be missing, so also walk the lot lines and ask the neighbors.
- Can a driveway cross the sewer line to my septic tank?
- Plan for it carefully. Keep vehicles off the tank and the drainfield, because weight crushes pipe and compacts the soil. Where the sewer line itself has to pass under a plowed driveway, frost goes deeper there, so the line needs full cover or insulation board at the crossing.