The Order of Site Work for a New Home on the Kenai Peninsula
The order of site work for a new home on the Kenai Peninsula is: survey and stake, soils and perc test, permits, clearing, access road, building pad, foundation dig, utilities (well, septic, and power), backfill, and final grade. The survey, the soils test, and the permits come first because they decide where the house, drainfield, and well can legally go. Almost every story about paying for site work twice starts with a machine moving dirt before those answers were in.
The order of site work for a new home, step by step
- Survey and stake. A licensed land surveyor finds and marks the property corners, then stakes the house, the driveway, and any setbacks. If there is water on or near the lot, have the surveyor show the 50-foot habitat setback and any mapped floodplain.
- Soils and perc test. A test hole shows whether the ground can take a conventional septic system or needs an engineered one, and where it can go. The drainfield then controls where the well can go, because state rules require at least 100 feet between a private well and a septic tank or drainfield.
- Permits and power application. A driveway permit if you tie into a borough road, or a state permit for access onto a state highway. Add a floodplain, habitat, or Army Corps wetland permit where they apply, and a city building permit inside city limits. Apply for Homer Electric service now as well.
- Clearing and grubbing. Clear the house site, driveway, septic area, and power route in one mobilization, once HEA has staked its route.
- Access road and driveway. Build the driveway section at least to a solid working surface, so concrete trucks, the well rig, and gravel trucks can get in without destroying it.
- Building pad. Strip the organics under the footprint, then place and compact structural fill in lifts up to the elevation the plans call for.
- Foundation dig. Excavate for the footings or foundation to the depth the design requires for frost, then the foundation crew forms and pours.
- Utilities. Drill the well, install the septic tank and drainfield, and trench for underground power and the water and sewer lines to the house.
- Backfill. Backfill around the foundation and over the utility trenches in compacted lifts, with foundation drainage in place where the design calls for it.
- Final grade. Shape the ground so water runs away from the house, finish the driveway surface, and spread topsoil or seed where you want it.
The perc test is the step people most want to skip and most regret skipping. Our guide to the perc test and soils test explains what the test involves.
Who does what on a new home site
| Step | Who usually does it | What to know |
|---|---|---|
| Survey and staking | Licensed land surveyor | Book early; the wait for a slot is often longer than the fieldwork |
| Soils and perc test | Engineer or qualified tester, with an excavator digging the test hole | Needs thawed ground |
| Septic design | Engineer, for engineered systems | The design sets drainfield size and location |
| Driveway permit | Owner or contractor, through the KPB Road Service Area or Alaska DOT&PF | The approach and culvert get built to the permit |
| Power | Homer Electric Association designs and builds the line; the owner clears the route and supplies the meter base | Design and engineering fee due with the application |
| Clearing, driveway, pad, excavation, backfill, final grade | Excavation contractor | One contractor on all of these avoids gaps between trades |
| Well | Well driller | Location is fixed by the septic separation distance |
| Septic installation | Installer or excavation contractor working to the approved design | Follows the state approval process for the system type |
| House wiring and meter base | Licensed electrician | HEA requires the meter base to pass inspection before it schedules construction |
| Foundation | Foundation or concrete contractor | Needs a pad built and compacted to plan |
Power is the piece that runs on the longest outside clock. Homer Electric's new home process starts with an application and a design and engineering fee. An HEA engineering tech then visits the site, stakes the route, and approves the meter base location. Easements, permits, and route clearing all have to be finished before the job is released to construction, jobs are scheduled in the order they are released, and HEA notes some permits on its end can take three weeks or more. Apply as soon as you know where the house goes.
What can run at the same time
Not every step has to wait in line. These commonly overlap:
- The permit applications and the HEA application can go in the same week the survey is done. They run on other people's clocks, so start them first.
- Clearing the power route can happen with the rest of the clearing, as long as HEA has already staked it. That often means waiting for HEA's site visit before clearing that strip.
- The well can be drilled once the drainfield location is fixed. Drilling early gives the builder water during construction.
- Trenching for power, water, and sewer lines can often happen in one open-ground window with one machine, as long as the separation distances are worked out on paper first.
- The septic system can go in while the house is being framed, as long as no trucks or equipment will cross the drainfield afterward.
Where people end up paying twice
- Building the pad before the perc test, then learning the only good drainfield spot is under the house.
- Drilling the well before the septic design, then finding the drainfield cannot get 100 feet away from it.
- Finishing the driveway surface before the heavy traffic. A well rig, concrete trucks, and loaded gravel trucks will rut a driveway that was only built for cars.
- Clearing the house site, then bringing the machine back later to clear the power route and septic area.
- Backfilling before the utility lines and foundation drain are in and checked, then digging it back out.
- Placing fill in a floodplain, wetland, or habitat setback without a permit, and being told to remove it.
- Final grading and topsoil before the septic goes in, then redoing both after the installation tears them up.
- Digging before calling Alaska Digline, which does not mark private lines such as the power line you buried to the shop. HEA reminds members that privately owned underground lines are the owner's job to locate. See our post on calling 811 before you dig.
How long site work takes before you can build
Most of the waiting is paperwork and scheduling, not machine time. The survey slot, the perc test report, the permits, and the HEA job queue usually take longer than the dirt work. Army Corps wetland permits commonly run several weeks to a month or more, which can cost you a season if you start late.
The machine work on a simple rural lot moves quickly once it starts. Deep organics, a long driveway, or a pad that needs a lot of imported fill add days to weeks. Well drilling time depends on how deep the driller has to go to find water, and that varies widely across the peninsula. Ask each party for their current lead time when you call, because it changes through the season.
Plan the order around the season
Soils testing and compaction both need thawed ground, and the good summer slots fill early. If you want to break ground in spring, get the survey and perc test done the fall before, put the permits and the HEA application in over the winter, and book your excavation contractor before breakup. Our month by month scheduling guide has more on what each part of the year is good for.
MNA Construction handles the dirt side of a new home on one schedule: clearing, driveway, building pad, foundation excavation, septic and utility trenching, backfill, and final grade, coordinated around your surveyor, well driller, and HEA. Request a free estimate and bring your survey and perc results if you have them, and we will lay out the order of work for your lot.
Common questions
- What comes first, the well or the septic system?
- The septic location comes first. Alaska rules require at least 100 feet between a private well and a septic tank or drainfield, and the soils test decides where the drainfield can go. Once that spot is fixed, the well can be placed and drilled, often early in the job so the builder has water.
- Do I need a perc test before building on the Kenai Peninsula?
- If the house will be on a septic system, yes in practice. The septic design starts with a soils and perc test, and that test also tells you which parts of the lot you should not build on. Do it before the house position is final and before any pad work.
- How early should I apply for power from Homer Electric?
- As soon as you know where the house will sit. HEA handles applications in the order received, needs a site visit to stake the route and approve the meter base location, and requires easements, permits, and route clearing before construction. Some of its permits alone can take three weeks or more.
- Can site work for a new home be done in winter?
- Some of it. Clearing and some excavation work well on frozen ground, but soils tests and compacted fill need thawed material. Winter is a good time to clear, get permits, and apply for power so the pad and utilities can start as soon as the ground allows.