Perc Test on the Kenai Peninsula: How a Septic Soils Test Works
A perc test on the Kenai Peninsula is one part of a septic soils test: a machine-dug test hole near the planned drainfield, a log of every soil layer, and, for silty soils, a timed test of how fast water soaks in. Under Alaska DEC rules the hole goes at least 6 feet below the bottom of the planned drainfield, and the results decide whether the lot can take a conventional septic system or needs an engineered one. Do it before you close on land.
Alaska septic systems answer to the Department of Environmental Conservation (DEC) under 18 AAC 72. Our septic overview covers the approval path from start to finish. This post is about the test itself and what to do with a bad result.
What a perc test on the Kenai Peninsula involves
People say "perc test" for the whole job, but DEC's rules describe three separate pieces.
- The test hole. DEC requires a test hole or pit within 25 feet of the edge of the proposed drainfield, dug to at least 6 feet below the estimated bottom of the drainfield. On most Kenai lots that means an excavator, because the hole often ends up 9 to 12 feet deep (the math is below).
- The soil log. Each layer gets classified using the Unified Soil Classification System, a standard set of letter codes such as GW for clean gravel, SM for silty sand, and ML for silt. The log also records depth to water, any seeps, and any bedrock or hardpan.
- The percolation test. Water is poured into a small hole in the soil layer where the drainfield will sit, and the tester times how fast the level drops, in minutes per inch. DEC requires a perc test for silty sand (SM), silty gravel (GM), and silt (ML). Cleaner sands and gravels can often be sized from the soil log alone.
The soil type and perc rate together set how much drainfield you need. These are DEC's application rates for a conventional system, from 18 AAC 72.530.
| Soil type | Perc rate (minutes per inch) | Drainfield area per bedroom |
|---|---|---|
| Gravel (GW, GP) | Faster than 1 | 150 sq ft, only with a 2 foot sand liner |
| Gravel (GW, GP) | 1 to 5 | 125 sq ft |
| Medium to coarse sand (SW, SP) | 1 to 15 | 150 sq ft |
| Fine sand or loamy sand (SP-SM) | 6 to 15 | 190 sq ft |
| Sandy loam, silty gravel, silty sand (GM, SM) | 16 to 30 | 250 sq ft |
| Loam, silt loam, silt (ML) | 31 to 60 | 335 sq ft |
| Silty clay loam, clay loam | 61 to 120 | Not allowed for conventional |
Soil slower than 60 minutes per inch needs an engineer's design and DEC approval before construction. Soil slower than 120 minutes per inch is treated as impermeable. Clay, organic silt, and peat also require an engineered design.
Who can do the soils test
Who is allowed to log the hole and run the perc test depends on who will install the system.
- A DEC certified installer can classify the soil and run the perc test for a conventional system they install under their own certification. To be certified, a person must hold (or work under) an Alaska general, excavation, or water and sewer contractor license and pass DEC's training and exam. Ask for the certificate number and check it against DEC's current certified installer list.
- An approved homeowner (someone who took DEC's homeowner course to install a system on their own owner-occupied home) cannot classify their own soil. They need a sieve analysis from a registered engineer or soils lab, or an engineer's visual classification and perc test, plus a soils report from the engineer.
- A registered engineer handles any system that needs an engineered design. For those, perc tests must be run by an engineer or someone working under one, and the soils report must carry the engineer's seal.
MNA digs the test holes with the machine and backfills them when the logging is done. The person signing the soils log is the engineer or certified installer on your project.
Groundwater and bedrock separation: the numbers that decide your system
The test hole exists to answer one question: how much clean, unsaturated soil sits under the drainfield. DEC's minimum vertical separations for a conventional system, from the bottom of the drain rock, are:
- 4 feet to the annual high water table
- 6 feet to an impermeable layer such as bedrock, clay, permafrost, or soil slower than 120 minutes per inch
Frost protection stacks on top of that. On the Kenai Peninsula, every part of a conventional system needs 4 feet of soil cover. DEC lets you substitute approved insulation for up to 2 feet of that cover, but never less than 2 feet of soil.
Here is how that plays out. Say the distribution pipe sits under 4 feet of cover and the drain rock below it is about 1.5 feet thick. The bottom of the rock is about 5.5 feet down. Add the 4 foot groundwater separation and the seasonal high water table needs to stay below roughly 9.5 feet. Bedrock or clay needs to be below about 11.5 feet. With insulation and 2 feet of soil cover, those numbers drop by about 2 feet. Your designer sets the real depths, but the math shows why many Kenai lots end up with a raised system.
Horizontal distances matter too. A drainfield or tank must be at least 100 feet from a private well and 100 feet from a lake, river, stream, spring, or slough. The drainfield must also stay 50 feet back from a slope steeper than 25 percent that drops more than 10 feet.
Why spring and fall test results can differ
Groundwater on a lot rises and falls through the year. A hole dug in a dry stretch of summer can show dry soil at 10 feet on a lot where water comes up to 5 feet during spring breakup or after heavy fall rain. The drainfield has to work at the wettest time of year, so the test has to find the seasonal high. The level on the day of the dig is only one reading.
DEC's rule for engineered systems lists the accepted ways to find the seasonal high water table:
- Monitoring test holes or soil borings between June 1 and September 30
- Reading soil mottling, the rust orange and gray blotches that form where water sits for part of the year
- Interpreting standing water levels nearby
- The engineer's experience from past work in the area
If a dry hole shows staining at 6 feet, water gets there at some point, and the design has to respect that line. DEC also bars the simpler no-plan-approval route on sites where groundwater comes within 4 feet of the surface or the soil is overly wet at any time of year.
Get the soils test done before you buy land
A soils test is the cheapest way to find out if a lot works for a house. Make the purchase contingent on it, and dig where the house and drainfield will actually go. A good result in the wrong corner of the lot does not help.
A few more checks worth making before closing:
- Ask DEC for any wastewater records on the parcel. DEC's fee to search and copy records by legal description is $25.
- Ask neighbors how their systems perform. DEC does not allow the simpler conventional route in areas where conventional systems are known to perform poorly.
- Look for low, wet ground and standing water. Our post on whether your lot is wetlands covers the warning signs.
- Leave room for a second drainfield. Engineered alternative systems submitted to DEC for approval must show an area reserved for a replacement field.
Our land buying checklist covers access, power, and the rest of the due diligence.
What a failed perc test means
A failed test means a conventional system will not work in that spot as designed. It does not automatically mean the lot cannot be built on. Before redesigning, it is often worth digging a second hole elsewhere on the lot, because soils on the peninsula can change a lot over a short distance.
If the soil still does not work, DEC treats the remaining options as alternative systems, which an Alaska registered engineer designs.
- Mound or raised bed. Imported sand and gravel build the drainfield up above the native ground to gain separation from water or bedrock. These usually use a pump and pressure distribution (a pump pushes effluent through small pipes so it spreads evenly).
- Advanced treatment unit. A treatment tank cleans the wastewater well beyond what a septic tank does before it goes to a drainfield. DEC requires the unit to carry current certification from an accredited third-party testing organization, or a one-year monitoring plan. Expect power, service visits, and an operation and maintenance manual you sign for.
- Holding tank. The last resort. When a holding tank goes to DEC for approval, the plans must justify a holding tank as the most practical option for the site, hold at least two days of flow, and have an audible alarm and a visual beacon that tell you when it needs pumping. You pay for pumping for as long as you live there.
For a home with up to 1,500 gallons per day of design flow, an alternative system can be built without prior DEC plan approval if an engineer designs it and supervises construction. The engineer then registers it with DEC within 90 days.
Get your test holes dug right
MNA Construction digs septic test holes with an excavator, deep enough for the engineer or certified installer to log the soil and find the seasonal high water line, then backfills them safely. If the lot passes, we build the system. If you are looking at land or planning a build anywhere from Soldotna to Homer, request a free estimate and we will schedule the dig. You can also see our septic system services.
Common questions
- How deep is a perc test hole in Alaska?
- DEC requires the test hole to reach at least 6 feet below the estimated bottom of the drainfield. Because Kenai Peninsula systems need 4 feet of frost cover, the drainfield bottom often sits 3.5 to 6 feet down, so the test hole commonly ends up around 9 to 12 feet deep.
- Who can perform a perc test in Alaska?
- A registered engineer, or someone working under one, can run perc tests for any system. A DEC certified installer can run the perc test for a conventional system they install under their own certification. Homeowners installing their own system need an engineer or soils lab to classify the soil.
- Does the Kenai Peninsula Borough issue septic permits?
- No. Septic systems in Alaska are regulated by the Department of Environmental Conservation under 18 AAC 72. Conventional systems built by a certified installer are registered with DEC after construction, and engineered systems go through a DEC registered engineer.
- How much does a perc test cost on the Kenai Peninsula?
- DEC's fee schedule has no separate fee for the soils test itself. The cost is the machine time to dig and backfill the holes plus the engineer's or installer's time to log the soil and write the report. More holes, deeper holes, and hard access all add to it, so get a quote for your specific lot.