Water and Sewer Connection in Soldotna and Kenai: Fees and Depth

MNA Construction··6 min read

A water and sewer connection in Soldotna starts with a water/sewer permit from Soldotna Public Works ($212 with tax), plus expansion fees of $250 for water and $500 for sewer on a typical 3/4 inch residential line, and a contractor who is bonded with the city. In Kenai, the water connection permit and the sewer permit are $300 each, and the connection must be made by a City-licensed contractor and inspected by Public Works. Then comes the trench, which is deeper than most people expect. Soldotna's standard specifications call for 10 feet of cover over a water service line.

This post covers who to call, what the cities charge, who is responsible for which part of the line, and what happens to your old well and septic tank.

Who to call first

Soldotna. New physical connections go through Public Works at 907-714-1241 or publicworks@soldotna.org. The city's pre-construction checklist also asks you to call the Utility Manager at 907-714-1205 for an on-site consult before work starts, which is worth doing. Account setup is at City Hall, 907-262-9107. The city posts water and sewer maps on its utility requirements page.

Kenai. The City of Kenai says new construction connections need a permit from the Building department. Public Works is at 210 Fidalgo Avenue, 907-283-8236, and the Water and Sewer Department is at 907-283-7535, option 2. Kenai also posts water and sewer availability maps on its water and sewer page.

Do you have to connect?

In Soldotna, properties within 300 feet of an existing main are required to connect. In Kenai, any structure that will use water and sits within 200 feet of an existing water main must connect under KMC 17.10.010. Outside those areas, homes run on wells and septic systems, which answer to the state Department of Environmental Conservation (DEC).

If you are buying in town, check the maps before you assume either way. A lot a few hundred feet past the end of a main can mean a well and septic, or a main extension paid for by the owner or developer.

Soldotna and Kenai connection fees

These are the city fees only, from the current fee schedules posted by both cities. Excavation, pipe, insulation, and restoration are separate.

FeeSoldotnaKenai
Water/sewer permit$212 (includes one initial inspection and one re-inspection)$300 water, $300 sewer
Water expansion fee, 3/4 inch line$250Not listed
Sewer expansion fee, 3/4 inch line$500Not listed
Account setup or deposit$53 account fee$100 deposit, refundable after two years of timely payments
Extra re-inspection$212 for the first 2 hours, $106 per hour afterNot listed
Driveway permit if not pulled with a building permit$25$25

Soldotna's expansion fees go up with line size. A 1 inch line is $468 for water and $938 for sewer. Kenai adds 6 percent sales tax to fees that are not exempt.

Two Soldotna rules affect scheduling. The contractor must have a bonded contractor packet on file (a $5,000 surety bond plus liability insurance) before the city issues the permit. And a water or sewer permit expires on December 31 of the year it was issued, so a permit pulled in October has a short window before freeze-up.

Who owns which part of the service line

The service line is the pipe from the city main to your house. In Soldotna's standard specifications, the sewer stub runs from the main to 5 feet inside the property line or past the edge of the easement. The water service has a brass curb stop (a shutoff valve) in a key box. From there to the house is the on-property service, and that is your permit, your contractor, and your cost.

Kenai's code puts the full cost of the service connection and any extension on the property owner, and only City personnel may operate the valve in the key box. Both cities require a separate service for each building and do not allow a service line to cross a neighboring property.

One warning from Soldotna's specifications: lines built without permits or city acceptance are "bootlegged," and the city is not obligated to repair them if they freeze or break. Ask the utility in writing which part of the line it maintains before you buy or build.

How deep the trench has to be for freeze protection

Soldotna's posted standard specifications set these depths. The document is an older scanned spec, so confirm the current numbers at your pre-work consult.

LineRequired coverWhen insulation is requiredWhen the city must approve
Water service10 feet, to a point 5 feet inside the footingsLess than 10 feet: 2 inches of insulationLess than 6 feet
Sewer service8 feet wherever it can be keptLess than 5.5 feet: 2 inches of insulationLess than 4.5 feet

Other Soldotna requirements that shape the trench:

  • Water and sewer lines at least 10 feet apart side to side and 18 inches apart vertically
  • Sewer slope of at least 1/4 inch per foot, laid in straight runs
  • A sewer cleanout within 2 feet of the foundation, every 90 feet, and at bends of 45 degrees or more
  • A backwater valve if the lowest drain in the building sits below the top of the nearest sewer manhole
  • Non-frost-susceptible backfill in the right-of-way (clean sand or gravel that drains instead of holding water and heaving)

Kenai's depth standard was not in the documents we found. Ask Kenai Public Works for its current service line requirements before you price the job.

What a typical service trench looks like

  1. Call 811 at least two business days before digging. Our Alaska Digline guide explains what gets marked and what does not.
  2. Dig to grade. A 10 foot water trench needs a protective system, because federal OSHA rules require sloping, shoring, or a trench box in any trench 5 feet or deeper unless it is cut in stable rock.
  3. Place bedding under the pipe, set the pipe, and tamp bedding carefully along its sides. Soldotna's details require over-excavation and replacement with suitable bedding where the native soil under the pipe does not meet spec.
  4. Lay insulation board over the pipe anywhere cover is short. Soldotna's detail shows rigid foam board (Dow Styrofoam HI or equal).
  5. Post the permit on site and call for the inspection before backfill. The contractor or a representative must be present.
  6. Backfill, then restore the right-of-way to its original condition, which Soldotna requires of every bonded contractor.

Abandoning the old septic tank and well

Kenai's utility rules require existing wells, septic tanks, and similar private systems to be disconnected and abandoned once city service starts. Soldotna's specifications spell out how a septic tank, cesspool, or seepage pit gets abandoned when a property connects to sewer:

  1. Pump the sewage out.
  2. Remove the lid or top of the tank.
  3. Fill with earth, sand, gravel, concrete, or other approved material up to the top of the sidewalls or the outlet pipe.
  4. Call for inspection.
  5. After inspection, fill to ground level.

For the old well, DEC's rules require the owner of a well to either maintain it or decommission it following DEC's well decommissioning practices. A well left open is a direct path for surface water into the aquifer. Ask the city whether it allows a well to stay in service for irrigation before you assume it does.

If the old tank is steel or the yard also hides a heating oil tank, our demolition and tank removal work covers pulling it out instead of filling it in place.

Connect your lot with one crew

MNA Construction digs and backfills water and sewer service trenches in Soldotna and Kenai, sets the bedding and insulation board, coordinates the city inspection, and abandons the old septic tank in the same mobilization. See our utility installation work or our pages for Soldotna and Kenai, then request a free estimate.

Common questions

How much does it cost to hook up to city water and sewer in Soldotna?
City fees for a typical home with a 3/4 inch line come to about $1,015: a $212 permit, a $250 water expansion fee, a $500 sewer expansion fee, and a $53 account fee. The trench, pipe, insulation, and backfill are separate and depend on the length and the 8 to 10 feet of cover the city requires.
Do I have to connect to city water and sewer if I have a well and septic?
In Soldotna, properties within 300 feet of an existing main are required to connect. In Kenai, a structure that uses water and sits within 200 feet of a water main must connect. When you do connect in Kenai, the old well and septic tank must be disconnected and abandoned.
How deep does a water line need to be in Soldotna?
Soldotna's standard specifications call for 10 feet of cover over a water service line, measured to a point 5 feet inside the footings. Lines with less than 10 feet of cover need 2 inches of insulation, and anything under 6 feet needs approval from the city engineer.
Who is responsible for the water line from the street to my house?
The property owner pays for and owns the on-property service from the curb stop or sewer stub to the house. In Kenai, only City staff may operate the shutoff valve in the key box. Ask the utility in writing which part between the main and your property line it maintains.