Underground Power Trench for HEA New Service on the Kenai
To get underground power to a new home or shop on the Kenai Peninsula, you apply to Homer Electric Association (HEA) for new service, pay the design and engineering fee, and HEA designs and stakes the route. Your part is the site work: a 15 foot wide cleared path with the roots pulled, the route within 6 inches of final grade, a meter base installed to HEA specs, and any underground power trench built to HEA's SS-1 standard, with 3 or 4 feet of cover over the cable or conduit and an HEA inspection before backfill. The paperwork moves slower than the digging, so start early in the year.
Everything below comes from HEA's 2026 Electrical Service Requirements, its trench drawings, and the service extension section of its tariff (the rate and rules book approved by the Regulatory Commission of Alaska).
How HEA new service works
HEA lays out the process on its new home and business page.
- Preliminary cost estimate. Free, non-binding, and done without a site visit. You need your parcel ID.
- Application. Submit the new service application online or on paper, along with the design and engineering fee. HEA needs an easement on a recorded plat or other legal document, survey monuments at the property corners, and a site sketch showing future driveways, garages, fences, and parking.
- Site visit. An HEA engineering tech selects and stakes the route, approves the meter base location, and tells you what you are responsible for.
- Design and firm quote. HEA finalizes the cost. Permits, easements, and clearing are identified here but not pursued until you pay or arrange financing.
- Permits and prep. HEA says some permits take three or more weeks. Your meter base must pass HEA inspection before the job is released to construction.
- Construction. Jobs are scheduled in the order they are released.
You must also disclose site conditions that are not obvious, such as buried slash or French drains. HEA bills unusual conditions as non-standard construction, paid in advance.
What you provide and what HEA provides
| You (the member) provide | HEA provides |
|---|---|
| Clearing and grubbing (pulling stumps and roots) 15 feet wide, centered on HEA's stakes | Route selection, design, and staking |
| Route and meter location within 6 inches of final grade, with obstacles removed | Easements and permits it identifies, after payment |
| Meter base, conduit riser on the meter base, and two ground rods with a continuous ground wire | The meter and HEA's own lines and equipment |
| A safe spot on your property for any pad-mounted transformer, with 10 feet clear in front and 3 feet on the other sides | Ownership of the transformer and other equipment on your property |
| Owner-installed voids (empty conduit sleeves) under driveways, where HEA calls for them | Inspection of trenches, voids, and backfill |
| Marking your private buried lines: septic, drain tile, private electric | Service wire up to your meter base |
| All wiring past the meter, by your electrician |
HEA is responsible for the underground service wire only up to your meter base. HEA's clearing drawing also says clearing is not permitted within 10 feet of an existing HEA facility or inside rights-of-way and easements. If you need the route cleared, that is the same work as land clearing for a house site, just narrower.
HEA's underground power trench spec
HEA's drawing SS-1 sets the rules for any trench that carries HEA cable or conduit.
- At least 12 inches wide, with a smooth, flat bottom clear of debris
- 2 inches of bedding under the cable or conduit and 4 inches of select material over it
- The first 6 inches of backfill free of rock, gravel, or anything that could cut the cable jacket, with nothing larger than 1 inch, compacted carefully
- If the native soil has rock over 1 inch, HEA-approved bedding material instead
- 3 or 4 feet from the top of the cable or conduit to final grade, as HEA designs it
- The rest of the backfill free of large rock and debris, mounded over the trench if not compacted so it can settle
- Spoils piled at least 24 inches back from the trench edge
- At least 12 inches of clear separation where the trench crosses another buried line
The trench has to follow HEA's staked alignment. HEA inspects the open ditch, must be on site to inspect the backfill, and will not energize the cable until backfill is complete with at least 36 inches of cover. HEA's tariff says no underground facilities may be buried before HEA inspects and approves them.
Driveway voids (drawing SS-21) have their own rules. HEA approves the route and length and sets the pipe size before you dig. The void must be buried at least 36 inches deep, extend at least 36 inches past each edge of the driveway or pavement, have sealed ends, and have a marker stake at each end. HEA inspects it before backfill.
The cost: design fee and the secondary service credit
HEA's tariff lists what drives the cost of a line extension: its length, the materials needed for the load, the terrain, access, and weather, whether it needs a primary extension (the higher-voltage line) or only a secondary service (the lower-voltage line from the transformer to your meter), and whether it is overhead or underground.
For a qualifying single-phase secondary service, you pay the design and engineering fee, the secondary service fee, any non-standard construction costs, and any cost sharing. HEA applies a secondary service credit, which is the most HEA will invest in the extension. In a 2026 filing with the Regulatory Commission of Alaska, HEA asked to raise the design and engineering fee from $500 to $1,000 and to set the single-phase credit at $5,800 (three-phase at $17,400). Confirm the current amounts with HEA Engineering before you budget.
Eligibility for the credit ties directly to site work. A site with a permanent foundation (poured concrete, sonotubes, or piling) qualifies if it also has two of these:
- A long-term potable water supply
- An appropriate septic or wastewater system
- An improved gravel driveway at least 50 feet long
- A gravel pad
Each parcel owner can receive only one secondary service credit, so a second service to a detached shop on the same parcel will not get one. One option is to feed the shop from your own panel or meter stub on your side of the meter, and that trench and wiring are yours.
Joint trench with ENSTAR, phone, or fiber
ENSTAR's crews install the gas service line from the street to your structure, and ENSTAR handles the locates and permits for it. You do not lay gas in your power trench. ENSTAR's excavation rules require electrical lines running parallel to a gas line to stay 36 inches away, and the same 36 inches from grounded parts like ground rods. Where lines only cross, clearance can drop to 12 inches. Plan your power route so it does not run alongside the future gas line.
For phone, cable, or fiber, ask both HEA and the provider before putting anything in the same trench. HEA's spec requires 12 inches of clear separation at crossings.
Your side of the meter: electrician and inspection
Everything past the meter belongs to you: the panel, the feeder to the house, and any line to a shop. HEA inspects the meter base but does not inspect your wiring, and its own guide recommends that the installation be inspected by the governing authority. Inside the cities of Kenai, Soldotna, Homer, or Seward, ask the city building department what electrical permit and inspection apply. The National Electrical Code sets burial depth on your side by wiring method, and your electrician picks the method.
Need power during construction? HEA will connect a member-furnished temporary meter base of up to 200 amps for no more than 12 months.
Call 811 before any digging
Alaska Digline needs at least two business days' notice, and no more than 15. When you hire a contractor, Alaska law puts the duty to request locates on the excavator (your contractor). The utilities mark only their own lines. Your septic, drain tile, and private electric lines are not marked, which is why HEA asks you to mark them before its crew arrives. Our 811 guide covers the details.
Get the site ready for HEA
MNA Construction clears and grubs the 15 foot HEA route, digs and backfills the trench to HEA's SS-1 spec with clean bedding, installs driveway voids, and builds the driveway and pad that help a site qualify for HEA's service credit. We work from Soldotna to Homer. See our utility installation and grading and land clearing services, then request a free estimate.
Common questions
- How deep does HEA require underground power lines to be buried?
- HEA's SS-1 trench drawing calls for 3 or 4 feet from the top of the cable or conduit to final grade, as HEA designs it, and HEA will not energize a service cable until it has at least 36 inches of backfill. Driveway voids must be at least 36 inches deep.
- How long does HEA take to install new service?
- It depends on the job and the season. HEA says some permits take three or more weeks, the meter base must pass inspection before the job is released, and jobs are built in the order they are released. Apply in late winter or early spring if you want power before freeze-up.
- Can I dig my own trench for HEA's underground line?
- HEA's trench spec applies to whoever digs the trench and makes that party responsible for calling for locates. HEA approves the route, inspects the open trench, and must be present for backfill. Confirm with HEA Engineering what your job allows, because member-built line extensions must use an HEA-approved electrical contractor.
- Does HEA charge for a new service connection?
- Yes. You pay a design and engineering fee with the application, plus the secondary service fee and any non-standard construction costs. HEA applies a secondary service credit to qualifying sites. The preliminary cost estimate is free.