Commercial Site Development on the Kenai: A Permit Checklist
Commercial site development on the Kenai Peninsula runs through four sets of approvals: land use from the city or borough, building plan review from the State Fire Marshal or your city, DEC review of the wastewater and water systems, and an access permit from whoever owns the road. Add a stormwater permit if you disturb an acre or more. The approvals with the longest lead times, such as a state highway driveway permit, should start before the site work is bid.
Here is the checklist we would want a new commercial owner to work through, in the order that keeps the dirt work from waiting on paperwork.
Step 1: zoning inside cities, almost none outside
Inside Kenai, Soldotna, Homer, and Seward, city zoning decides what can be built and where. Soldotna requires zoning permits. Kenai's site plan rules require the plan's snow storage, snow removal, and drainage to fit the surrounding area. Homer requires a zoning permit before clearing or new construction. Call the planning office with a sketch before you buy or design.
Outside the cities, the borough's local option zoning page says it does not generally restrict land use in its Rural District, except in overlay districts. The ones that catch commercial sites:
- The 50-foot habitat protection district along cataloged salmon streams
- The floodplain district, in mapped flood zones
- A local option zoning district, if owners in a subdivision asked the borough for one
- Inside Soldotna, the Kenai River Overlay District near the river
Recorded covenants on the subdivision can also limit commercial use. Read them. Work near salmon water or in a floodplain goes through the Kenai River Center's single application.
Step 2: building plan review
A commercial building in Alaska needs plan review before work starts. The State Fire Marshal's Plan Review Bureau reviews construction, additions, remodels, and changes of occupancy, plus fuel tank installations. The only exemption it lists is residential housing of three units or fewer.
Some cities do their own review instead. On the Kenai Peninsula, those deferred jurisdictions are Kenai, Soldotna, and Seward. Projects in Homer, Sterling, Nikiski, Kasilof, and the rest of the borough go to the state.
What the state says about timing:
- Plans are reviewed after the fee is paid, typically in two to four weeks.
- Work started before approval adds a special processing fee equal to the standard review fee.
- A building cannot be occupied until its plans have been examined and approved.
The site plan matters to the fire review. The state adopts the 2021 International Fire Code, which sets rules for fire apparatus access roads, including width and how close the road comes to the building. Ask the reviewer what your site needs before the parking layout is final.
Step 3: wastewater
If the site is not on city sewer, the septic system is a DEC decision, and the size of the business decides the path.
| Situation | DEC path |
|---|---|
| Small commercial facility on one lot, design flow 1,500 gallons per day or less, conventional system in suitable soils | Can be installed without prior approval by a DEC-certified installer (18 AAC 72.511) |
| Several buildings owned by one entity, up to 2,500 gallons per day | Engineer designs it and supervises construction |
| Anything larger, or soils and groundwater that do not fit | Prior written DEC approval, with plans sealed by a registered engineer (18 AAC 72.200 and 72.205) |
Shop floor drains need their own plan. Federal injection well rules have prohibited new motor vehicle waste disposal wells since April 5, 2000, so a shop floor drain cannot empty into the ground. It goes to a holding tank or an approved system.
On city sewer, connection is usually required. Soldotna requires properties within 300 feet of an existing main to connect, and Kenai requires a structure within 200 feet of a water main to connect. Our water and sewer connection post covers fees and depth.
Step 4: water, and when a well becomes a public water system
A well serving the public can turn into a regulated public water system. Under DEC's drinking water rules, 18 AAC 80.1990, a public water system has at least 15 service connections or regularly serves an average of at least 25 people daily at least 60 days a year.
- A store, restaurant, lodge, or campground serving 25 or more customers a day for 60 days a year is a transient non-community system.
- An office or shop where the same 25 or more people drink the water for more than six months a year is a non-transient non-community system.
Owners of those systems need DEC's prior written approval of engineering plans before building or operating them, under 18 AAC 80.200. Public water system wells also need larger separation from septic systems: 200 feet from septic tanks and drainfields. Plan the well and the septic together on the site plan.
Step 5: access from the road
Who owns the road decides the permit.
- State highways. The Sterling, Kenai Spur, Seward, and other state routes need a DOT&PF driveway or approach road permit under 17 AAC 10.020. DOT&PF's paper application says to apply at least 60 days before construction, with a recorded plat, a site plan showing the driveway and parking, and proof of ownership. A traffic impact analysis is required if a commercial site will generate 100 or more vehicles per hour. Apply through dot.alaska.gov/permits.
- Borough roads. A borough driveway permit, a culvert of at least 15 inches by 30 feet, and a grade no steeper than 4 percent within 50 feet of the road.
- City streets. The city's public works department.
The DOT&PF permit is often the long pole. Start it as soon as the site plan shows the driveway location.
Step 6: stormwater, drainage, and utilities
If the project disturbs an acre or more, including clearing, the spoils pile, and snow storage areas, it needs coverage under DEC's Construction General Permit and a written stormwater plan. Our APDES stormwater permit guide covers the steps.
Permanent controls such as oil-water separators and detention ponds add a second review: engineering plans to DEC at least 30 days before construction. Our post on storm drain and catch basin installation explains when those are needed. For the lot itself, see commercial gravel parking lot design, which covers the gravel section, ADA spaces, and snow storage.
Then power and gas. Apply to Homer Electric for commercial service early, because the line extension and transformer have to be designed and scheduled. Ask ENSTAR whether gas is available at the lot line. Then plan one trench route for the utilities where the providers allow it. Before any digging, Alaska Digline needs two working days of notice.
Commercial site development sequence and timeline
| Order | Task | Lead time to plan for |
|---|---|---|
| 1 | Zoning check, covenants, survey | Before purchase or design |
| 2 | DOT&PF driveway permit | Apply at least 60 days before construction |
| 3 | Soils testing for septic, well, and the pad | Needs thawed ground |
| 4 | DEC wastewater and water plan approval | Ask DEC when you apply |
| 5 | Fire Marshal or city plan review | Typically two to four weeks after payment, state review |
| 6 | Permanent stormwater controls to DEC | At least 30 days before construction |
| 7 | Stormwater plan and Notice of Intent | At least five business days before work starts |
| 8 | Clearing, pad, utilities, parking | The construction season |
MNA Construction does the site work for commercial projects on the Kenai Peninsula, around Soldotna and Kenai: clearing, the building pad, utility trenches, septic excavation, drainage, and parking. We work from your engineer's plans and can tell you early which permits our part of the job depends on. See our site preparation work, then send your site plan through our estimate request. Estimates are free.
Common questions
- Do I need a building permit for a commercial building outside city limits on the Kenai?
- The borough does not issue building permits outside the cities. A commercial building still needs plan review and approval from the State Fire Marshal before work begins. Septic, water, access, and stormwater approvals apply as well.
- How long does State Fire Marshal plan review take?
- The state says plans are reviewed after the fee is paid, typically in two to four weeks. Starting work before approval adds a special processing fee equal to the standard fee. Kenai, Soldotna, and Seward do their own reviews, so ask those cities for their timelines.
- Is the well for my business a public water system?
- It is if it has at least 15 service connections or regularly serves an average of 25 or more people a day for at least 60 days a year. A busy store, restaurant, or campground usually qualifies. Public water systems need DEC approval of engineering plans before they are built or operated.
- Do I need a traffic study for a driveway onto a state highway?
- DOT&PF's application calls for a traffic impact analysis if a commercial site will generate 100 or more vehicles per hour. Smaller sites still need a driveway permit with a plat and site plan. Apply at least 60 days before construction.