Costs

Commercial Gravel Parking Lot in Alaska: Design and Cost

MNA Construction··7 min read

The cost of a commercial gravel parking lot or equipment yard on the Kenai Peninsula comes down to its gravel section, its drainage, and how much bad ground has to come out, and all three are set by the trucks that will use it. Plan a thicker section than a house driveway, a place for plowed snow that is not the borough ditch, accessible parking if the public parks there, and a stormwater permit if the project disturbs an acre or more. Inside Kenai and Soldotna, the lot also goes through city site plan or zoning review before the first load arrives.

A lot that ruts out in its first breakup becomes a rebuild with customers parked on it. Here is how to plan one.

The gravel section for truck traffic

A customer lot for pickups and cars is one thing. A yard where loaded dump trucks, fuel trucks, and lowboys turn and park is another. Turning tires twist and tear gravel, and parked loads sit in one spot through breakup.

The Kenai Peninsula Borough's road standards make a useful benchmark. A borough road serving 21 to 50 lots is built with 24 inches of coarse Type I gravel under 6 inches of Type II surface gravel. Its largest roads add another 6 inches of crushed Type III and need an engineer's design. A commercial yard carrying loaded trucks should not get less than that on poor soil.

  • Strip the organics down to firm mineral soil across the whole lot.
  • Lay geotextile fabric over silts. The borough requires it over F4 soils, the most frost prone class, on its roads.
  • Build in lifts of 12 inches or less, each compacted.
  • Cap with a crushed surface course that has some fines, or with D-1 if you plan to pave soon.

For heavy equipment yards or wet ground, have a geotechnical engineer size the section. A soils report costs far less than rebuilding a lot.

The borough also uses a field test you can borrow, the proof roll: a 12 cubic yard end dump loaded to legal capacity drives the road, and ruts deeper than 3 inches mean the road needs more work. Run the same test on your lot before you open it.

Gravel quantity math for a commercial gravel parking lot

Here is the math for a 180 x 120 foot lot (21,600 square feet, about half an acre) with a 30 inch section: 24 inches of coarse gravel under 6 inches of surface course.

StepMathResult
Coarse gravel, 24 inches180 x 120 x 2 / 271,600 compacted cubic yards
Surface course, 6 inches180 x 120 x 0.5 / 27400 compacted cubic yards
Loose yards to order2,000 x 1.2 to 1.32,400 to 2,600 loose cubic yards
Truckloads2,500 / 10 to 14 yards per loadabout 180 to 250 loads
Weight, if sold by the ton2,500 x 1.4 to 1.5about 3,500 to 3,750 tons
Fabric21,600 / 9, plus overlapsabout 2,400 square yards before overlaps
Strip 18 inches of organics, 10 feet beyond the edges200 x 140 x 1.5 / 27about 1,560 cubic yards of spoils

That spoils pile is the line people forget. Piled 6 feet high, 1,560 cubic yards covers about 7,000 square feet. Hauling it off instead adds 100 or more truckloads.

To price it, call a pit for per yard or per ton prices on each product and the delivery charge per load, then add equipment time for clearing, stripping, fabric, spreading, and compaction. Check that each bid lists the section depth, the products, and how spoils are handled.

Plan where the plowed snow goes

Decide where the snow goes before you decide where the parking stalls go. The borough's roads notice states that it is illegal to plow snow into roads, ditches, and rights of way from private property. A lot with no storage area ends up stacking snow on its own parking spaces or paying to haul.

The volume adds up fast. Every foot of snow plowed off that 21,600 square foot lot is 21,600 cubic feet. Stacked 8 feet high, it covers 2,700 square feet. Plowed snow packs denser and piles settle, but storms stack up over a winter, so size the storage area for a season, not a single storm. Our post on snow hauling vs stacking runs the numbers on when hauling pays.

Put the storage area:

  • On the downhill side, where meltwater drains away from the building and the parking area
  • Away from the well, the septic drainfield, wetlands, and streams, because the melt carries sand, salt, and oil
  • Clear of the entrance, so the pile does not block drivers' sight lines
  • On gravel built to carry the loader that pushes it

If you hire out the plowing, write the storage area into the contract.

Drainage and the access approach

Grade the lot so water sheds off the surface and into ditches or swales that carry it to a natural drainage, not onto the neighbor's lot or into the road. A gravel lot needs a few percent of slope to shed water, which conflicts with accessible parking (below), so plan the grades for both at the start.

The approach is regulated by whoever owns the road. A driveway onto a borough road needs a borough driveway permit, a culvert of at least 15 inches by 30 feet, and a grade no steeper than 4 percent within 50 feet of the road. Access onto a state highway goes through DOT&PF. Our post on Kenai Peninsula driveway permits covers both.

ADA parking: when it applies and what it takes

Businesses open to the public and commercial facilities fall under the federal 2010 ADA Standards. Where parking is provided, a share of the spaces must be accessible.

Total spaces in the lotAccessible spaces required
1 to 251
26 to 502
51 to 753
76 to 1004
101 to 1505

At least one in every six accessible spaces must be van accessible, so a small lot's single accessible space is a van space. The standards set the details:

  • Car spaces at least 96 inches wide; van spaces at least 132 inches wide, or 96 inches with a 96 inch aisle
  • An access aisle at least 60 inches wide, the full length of the space, marked so no one parks in it, and connected to an accessible route to the entrance
  • A sign with the International Symbol of Accessibility, at least 60 inches above the ground to the bottom of the sign, reading "van accessible" at van spaces
  • A surface that is stable, firm, and slip resistant, with no slope steeper than 1:48 (about 2 percent) in any direction

Loose gravel has a hard time meeting the firm and stable requirement, and plows and frost heave change its slope every year. Many owners pave or pour concrete for the accessible spaces, the aisle, and the route to the door, and keep the rest of the lot gravel. Lots used only by trucks, buses, or delivery vehicles are exempt from the parking count, but a lot the public uses needs a passenger loading zone instead.

Commercial building plans in Alaska go through State Fire Marshal plan review before work begins, except in deferred jurisdictions. Kenai, Soldotna, and Seward do their own review. Ask that reviewer which accessibility requirements they will check on your parking.

City rules, borough rules, and the stormwater trigger

Kenai. The City of Kenai's landscaping and site plan rules (KMC chapter 14.25) require the site plan's snow storage, snow removal, and drainage to be compatible with the surrounding area, and parking lots to meet the city's parking code. Those rules also exempt land zoned Heavy Industrial from a paving requirement, so ask the planning office whether a gravel lot is allowed in your zone before you design one.

Soldotna. Soldotna has city zoning and requires zoning permits. Take a sketch of the lot to city planning before you order gravel.

Outside city limits. The borough does not generally restrict land use in its Rural District. The rules you will meet are the driveway permit, the habitat protection district along salmon streams, and the floodplain district.

Stormwater. Under federal rules administered in Alaska through the APDES program, construction that disturbs 1 acre or more needs Construction General Permit coverage and a stormwater plan, and smaller pieces of a larger common plan count toward the acre. Disturbance counts everything you clear or dig, including the spoils pile, ditches, and snow storage area. The half acre lot above, with its stripping margin, spoils pile, and storage area, comes close to an acre. Our post on the APDES stormwater permit explains the process.

Building it now to pave later

If paving is in the plan, build the gravel lot as the pavement base. Set the final drainage grades now, use a crushed base like D-1 on top (the borough's own paving standard calls for D-1 base course), and leave room for the accessible spaces at their final slope. Letting the lot go through a breakup or two before paving shows you any soft spots while they are still cheap to fix.

MNA Construction builds commercial gravel lots and equipment yards on the Kenai Peninsula, from clearing and stripping through fabric, the gravel section, drainage, and the approach, including lots around Kenai and Soldotna. See our site preparation and snow removal services, then request a free estimate.

Common questions

How thick should gravel be for a commercial parking lot?
It depends on the soil and the trucks. For loaded truck traffic on poor soil, use at least what the borough requires on a busier road, 24 inches of coarse gravel under 6 inches of surface gravel, over fabric where the soil is silt. A geotechnical engineer should size the section for heavy equipment yards.
Do I need a permit to build a gravel parking lot on the Kenai Peninsula?
Outside cities, the borough does not require a land use permit for the lot itself, but the driveway onto a borough road needs a driveway permit and disturbing an acre or more needs stormwater permit coverage. Inside Kenai or Soldotna, expect city site plan or zoning review, and the building itself goes through plan review.
How many ADA parking spaces does a small business lot need?
Under the 2010 ADA Standards, a lot with 1 to 25 spaces needs 1 accessible space, and 26 to 50 spaces needs 2. At least one in six accessible spaces must be van accessible, so the first one is a van space with a wider aisle.
Can a gravel parking lot meet ADA requirements?
The accessible spaces, aisles, and route have to be stable, firm, and slip resistant, with slopes no steeper than 1:48. Loose or frost heaved gravel struggles to stay that way, so many owners pave or pour concrete for just those areas and keep the rest gravel. Confirm with your plan reviewer.

Planning excavation or site work in Southcentral Alaska?

MNA Construction is owner-operated and ready to help. Let's talk about your project.

Get a Free Quote