Septic & Utilities

Septic Tank Replacement and Abandonment in Alaska

MNA Construction··6 min read

Septic tank replacement in Alaska is a modification under DEC rules: a certified installer, a registered engineer, or an approved homeowner does the work, DEC gets notice at least one day before it starts, and the new tank is registered with photos within 90 days. The old tank gets pumped, then either pulled out or filled in place with earth, sand, gravel, or concrete. If you are in Soldotna or Kenai and close enough to a city main, connecting to sewer may replace the tank job entirely.

This post covers when a tank has to go, how the new one is sized and set, the DEC paperwork, and how to abandon the old tank the right way.

When a septic tank needs replacement

A tank that holds water and keeps solids out of the drainfield can run for a long time. These are the conditions that end it:

  • Rusted steel. Steel tanks rust through over time. A thin shell leaks, and a rusted lid can collapse under a person or a mower. If you know you have a steel tank, keep vehicles and people off it until it is checked.
  • Cracked or broken concrete. Cracks let groundwater in and effluent out. At breakup, a leaking tank can fill with groundwater and push it straight to the drainfield.
  • Wood parts. If your system has a wood lid, wood cribbing, or other wood that touches wastewater, it cannot simply be patched. DEC rules prohibit installing, modifying, or repairing a system with wood parts that contact wastewater.
  • A cesspool. DEC prohibits installing, modifying, or using a cesspool (a pit that takes raw sewage with no tank ahead of it). If that is what you have, it gets replaced with a real system or a sewer connection.
  • Too small for the house. Adding bedrooms raises the required tank size. A modification has to bring the system up to the current rules.
  • A tank that floats. A tank pumped empty during high groundwater can lift out of the ground. Tanks now have to be installed with anti-flotation measures.

If the drainfield is the part that failed, read our post on failing drainfield signs first. Replacing a good tank does not fix a dead field.

Replace the tank or connect to city sewer

Inside Soldotna, properties within 300 feet of an existing sewer main are required to connect. Inside Kenai, the city's residential permit packet says connection is required when the building footprint is within 200 feet of the existing water and sewer systems, and Kenai requires the old well and septic tank to be disconnected and abandoned once city service starts.

If you are inside one of those distances, a failed tank is usually the moment to connect instead of rebuilding. The permit fees, trench depth, and who owns which part of the line are in our water and sewer connection guide. Outside city service, which covers most of Sterling, Nikiski, and Kasilof, the tank gets replaced.

Sizing the new tank

DEC sizes home tanks by bedroom count, using a design flow of 150 gallons per day per bedroom. The minimums for a house:

  • 0 to 3 bedrooms: 1,000 gallons
  • 4 bedrooms: 1,250 gallons
  • 5 bedrooms: 1,500 gallons
  • Each added bedroom up to 8: another 250 gallons

A basement sump or lift station ahead of the tank adds 250 gallons to the minimum. Tanks of 2,000 gallons or less need a 4 inch cleanout that sticks up at least a foot above ground. Larger tanks need insulated, locking manhole risers to the surface. The full sizing table and what drives the price are in our septic system cost guide.

DEC rules for setting the new tank

Under 18 AAC 72.530, the new tank and its connections have to meet these requirements:

  • Tank design and construction meet the minimum specifications of the Uniform Plumbing Code, and DEC publishes material specifications for tanks.
  • The tank is installed to the manufacturer's specifications, with anti-flotation measures.
  • Mechanical watertight couplings join the pipe to the tank at both the inlet and the outlet.
  • Solid pipe without joints spans 5 feet from the inlet and outlet onto undisturbed earth, or the soil under it is backfilled and compacted in 6 inch lifts first.
  • The last 10 feet of sewer line before the tank runs at no more than 2 percent slope.
  • Every part of the system has 4 feet of soil cover on the Kenai Peninsula, or at least 2 feet of soil plus approved insulation.

Location is where tank jobs get complicated. DEC's rules say a modified system has to meet current separation distances, and those apply to existing components too. The tank has to sit at least 100 feet from any well and any lake or stream, and at least 5 feet from the drainfield. If the old tank sat 70 feet from the well, the new one cannot go in the same hole. Either it moves, or you request a waiver, which DEC charges $295 per standard to review.

DEC notice and registration steps

For a conventional system that does not need DEC plan approval, the sequence from 18 AAC 72.550 is:

  1. Hire a DEC certified installer or registered engineer, or complete DEC's homeowner training if you are doing your own owner-occupied home.
  2. Notify DEC at least one day before work starts. The notice includes the legal description, physical address and directions, the responsible person's name and phone number, and the scheduled date. If the date changes, notify DEC again before construction begins.
  3. Photograph each stage. DEC's list includes the septic tank with its inlet and outlet pipes, the sewer line and foundation cleanout, any lift station and alarm, insulation, and the finished grade with standpipes.
  4. Within 90 days of finishing, submit DEC's documentation of construction form with the photos, signed by the installer or homeowner or sealed by the engineer, with the registration fee ($115 under the current schedule).

Systems that need an engineered design follow the engineer's path, and some need DEC plan approval before work begins.

Abandoning the old septic tank

An old tank left empty and open is a hazard: it can collapse under a person or a machine, and it holds water. There are two accepted ways to deal with it.

MethodStepsBest fit
Fill in placePump, remove the lid or top, fill completely with earth, sand, gravel, concrete, or other approved materialConcrete tanks in open ground away from future building sites
RemovePump, dig out, haul the tank away, backfill and compact the holeSteel tanks, tanks under a future addition or driveway, or when the ground will carry weight

The Uniform Plumbing Code, which Alaska adopts as its state plumbing code, requires an abandoned septic tank to have the sewage removed and be completely filled with earth, sand, gravel, concrete, or other approved material. Soldotna's standard specifications spell out the sequence for properties connecting to city sewer:

  1. Pump the sewage out.
  2. Remove the lid or top of the tank.
  3. Fill with approved material up to the top of the sidewalls or the outlet pipe.
  4. Call for inspection.
  5. After inspection, fill to ground level.

A septage pumper empties the tank and takes the septage to an approved disposal site. Cap the old building sewer where it leaves the house or at the new tank so it cannot drain into the old one.

For steel, removal is often simpler than filling, because a rusted shell can collapse later and leave a sinkhole. Once a tank is pumped out and cleaned, the borough's landfills accept metal as inert waste. Call KPB Solid Waste to confirm what condition they need the tank in. Our demolition and tank removal work covers pulling and hauling old tanks.

Ask DEC (Soldotna office, (907) 262-5210) whether the old drainfield needs any work when you abandon a system. If no inspector is involved, take photos of the empty tank and the filled hole for your house records.

Replace your tank in one visit

MNA Construction handles the excavation, sets the new tank, and removes or abandons the old one in a single mobilization, working with the certified installer or engineer who files with DEC. In Soldotna and Kenai, we also dig the sewer connection when city service is the better answer. Request a free estimate or see our septic system services.

Common questions

Do I need DEC approval to replace a septic tank in Alaska?
A tank replacement counts as a modification. For a conventional system that needs no plan approval, the installer notifies DEC at least one day before work and registers the system with photos and a $115 fee within 90 days. Engineered systems follow the engineer's path, and some need DEC approval first.
Can I leave an old septic tank in the ground?
Yes, if it is abandoned properly. The plumbing code requires the sewage to be pumped out and the tank completely filled with earth, sand, gravel, concrete, or other approved material. Soldotna also requires an inspection before the final fill to grade.
Can the new septic tank go in the same hole as the old one?
Only if that spot meets current DEC separation distances, including 100 feet from any well and any lake or stream. DEC applies its distances to existing components when a system is modified, so an old tank that sat too close to the well usually has to move.
What size septic tank do I need for a 4 bedroom house in Alaska?
DEC's minimum for a 4 bedroom home is 1,250 gallons. Add 250 gallons if a basement sump or lift station pumps into the tank. Tanks larger than 2,000 gallons need insulated, locking manhole risers.