Hiring Guide

Excavation Contract Checklist: What to Include in Alaska

MNA Construction··5 min read

A written excavation contract in Alaska should spell out the scope and quantities, unit prices for the parts the ground decides, exclusions, how changes get approved, the schedule and weather terms, a payment schedule tied to progress, who pulls which permits, who calls for locates, the warranty, proof of registration and insurance, and how lien releases work. The state's homeowner guide says to get a written bid or contract and to put any changes in writing.

This post is general information, not legal advice. For a large job or a contract you are unsure about, have an Alaska attorney read it before you sign.

What an excavation contract should include

SectionWhat it should sayWhy it matters
ScopeEach operation, by name and locationSettles what the price buys
QuantitiesYards, tons, feet, square feetLets you check the work against the bid
Unit pricesRates for extra organics, rock, import, trenchPrices the unknowns before they happen
ExclusionsEverything not included, in writingKeeps surprises out of the final bill
Change ordersWritten and signed before extra workStops arguments after the fact
Schedule and weatherStart window, season limits, delaysSets expectations around breakup and freeze
PaymentAmounts tied to finished stagesKeeps payment behind the work
PermitsWho applies for which permitAvoids work stopping for paperwork
LocatesWho calls 811 and who finds private linesProtects buried lines and your wallet
WarrantyWhat is covered and for how longCovers settling, washouts, defects
Registration and insuranceRegistration number, certificate from the agentProves the contractor can legally do the job
LiensLien releases with paymentsProtects your title

Scope, quantities, unit prices, and exclusions

The scope should name each operation: clearing, stripping organics, excavation, imported fill placed and compacted in lifts, the driveway section, trenching, backfill, and final grade. Attach the site plan or survey so "the pad" means one specific place, and make sure the quantities match the estimate you accepted.

Unit prices handle what nobody can see until digging starts. If the contract says the base price assumes 18 inches of organics and sets a rate per cubic yard for anything deeper, then deeper organics change the quantity and nothing else. Do the same for rock. Define what counts as rock, such as material the machine on site cannot dig with a standard bucket, and set a rate for it. Without that definition, every large boulder becomes a debate.

Exclusions

Read this section first. Common exclusions in Alaska site work include rock, dewatering, hauling stumps and debris off site, engineering, permit fees, topsoil, and buried tanks or contaminated soil. If any of those turns up, the contract should say how it will be priced, usually at a unit rate or as a written change order.

Change orders and the schedule

Changes happen on almost every site. The contract should require a written change order, signed by both of you before the extra work starts, that states the added cost and any change to the schedule. The state's homeowner's guide to hiring a contractor says to put any changes to the agreement in writing. With unit prices already in the contract, most change orders become simple arithmetic.

Schedule and weather

Alaska site work runs on the ground's schedule. The contract should give a start window instead of a single date, and say what happens when weather or ground conditions stop work. Address these:

  • Breakup, when thawed soil sits on frozen ground and will not compact.
  • Spring weight restrictions on borough roads, which can delay hauling.
  • Freeze-up, when fill can no longer be placed and compacted.
  • Who pays to move equipment off and back on if the job stops partway.

Payment schedule tied to progress

The state guide says not to pay for work that is not complete, to pay as significant portions of work are done, and to keep detailed records of every payment. Tie each payment to a finished stage you can see, such as clearing done, pad built, or septic installed. A modest deposit to mobilize is normal, as our guide to reading an excavation estimate explains. If a construction loan is paying, line the payments up with the draws; our construction loan post covers how draws work.

Permits and utility locates

The contract should name who applies for each permit: the KPB driveway permit, any city building permit, a floodplain or habitat permit, and any Army Corps permit. The state guide says to call your city to find out who is responsible for building permits. Permit fees should show up either in the price or in the exclusions.

Under Alaska's one-call law, the person moving the dirt is the excavator, and the excavator gives Alaska Digline notice at least 2 working days before digging. A ticket stays active for 15 working days. Digline members do not mark private lines, such as a buried power line to a shop or a well line, so the contract should say who locates those. Our post on calling 811 before you dig has the full rules.

Warranty, registration, and insurance

Ask what the warranty covers and for how long, and get the answer into the contract. Common items are trench and backfill settlement, driveway soft spots, and culvert washouts. Spell out what is not covered, such as damage from heavy trucks you hired later.

The contract should list the contractor's state registration number and exact business name. Ask for a certificate of insurance sent directly from the insurance agent. Our post on checking an Alaska contractor license explains what to verify.

Lien rights and lien releases

Alaska's mechanics lien law is AS 34.35. Under AS 34.35.050, a general contractor, workers, material suppliers, equipment providers, and surveyors or engineers who work under a contract with the owner can claim a lien on the property for unpaid work. Here are the basics.

  • Notice of right to lien. Under AS 34.35.064, a contractor or supplier may give the owner written notice before starting work. If they do, the owner carries the burden of proving they did not know about or agree to the work.
  • Deadline to record a lien. Under AS 34.35.068, a claim of lien must be recorded within 120 days after the work or supply ends, unless the owner records a notice of completion.
  • Notice of completion. Under AS 34.35.071, the owner may record one after the project is complete. For claimants who never gave a notice of right to lien, the window then shrinks to 15 days after it is recorded.
  • Time to enforce. Under AS 34.35.080, a recorded lien stops binding the property after six months unless a court action is filed or an extension is recorded.

The practical step comes from the state guide: get a completed lien release before final payment. On a bigger job with subcontractors or suppliers, ask for releases from them too.

MNA Construction puts scope, quantities, unit prices, and exclusions in writing before work starts, and we are licensed and insured. If you are planning site preparation or a new home site anywhere from Kenai to Homer, request a free estimate and ask to see the contract terms with it.

Common questions

Do I need a written contract for excavation work in Alaska?
Get one. Alaska's homeowner guide to hiring a contractor says to get a written bid or contract and to put changes in writing. A written contract with scope, quantities, and exclusions is the only reliable record of what you agreed to.
How long does a contractor have to file a lien in Alaska?
Generally 120 days after the work or supply ends, under AS 34.35.068. If the owner records a notice of completion, claimants who never gave a notice of right to lien have only 15 days after it is recorded. Confirm deadlines for your situation with an attorney.
What is a lien release?
It is a signed document from a contractor or supplier stating they have been paid and give up their lien rights for that work. Ask for one before final payment, and from subcontractors and suppliers on larger jobs.
Who is responsible for calling 811 on an excavation job?
The excavator, which is whoever is moving the dirt. On a hired job that is usually the contractor, but the contract should say so in writing, along with who finds private lines that Alaska Digline does not mark.

Planning excavation or site work in Southcentral Alaska?

MNA Construction is owner-operated and ready to help. Let's talk about your project.

Get a Free Quote