Construction Loans and Site Work in Alaska: What Lenders Want
On a construction loan in Alaska, site work is usually the first money out the door, so lenders want it priced, itemized, and scheduled before they approve the loan. Expect to give the lender a line-item bid, follow a draw schedule that releases money as stages are done and checked, and carry a contingency for what the ground turns up. Every lender sets its own rules, so confirm each point below with yours.
This post explains how site work typically fits into a construction loan. It is not financial advice.
How site work fits a construction loan
A construction loan pays out in stages, called draws, instead of one lump sum. Under Fannie Mae's single-closing construction-to-permanent rules, the lender manages paying out the loan money to the builder, the contractor, or other approved suppliers. Many lenders send an inspector to confirm each stage before releasing the next draw.
Site work comes first on the ground, so it lands in the first draws: clearing, the driveway, the building pad, and the foundation excavation. Utilities, backfill, and final grade come later.
There are two common loan setups. A single-closing loan starts as a construction loan and converts to the permanent mortgage. A two-closing setup uses one loan to build and a second to pay it off. Fannie Mae caps any single construction period on a single-closing loan at 12 months and the total at 18 months, extensions included. A job that runs longer has to be handled as a two-closing loan. In Alaska, a late start that pushes work into a second season can bump into that limit, so plan the length of site work before you lock the loan.
What the lender wants to see from your excavation contractor
A lender reviewing a site work bid is asking two questions: is this the whole job, and can the draws follow it. A bid that helps answer both has these parts.
- Line items by operation. Clearing, stripping, driveway, pad, foundation dig, septic, utility trenching, backfill, and final grade, each with its own price.
- Quantities. Cubic yards of excavation and fill, tons of gravel, feet of trench.
- Unit prices for the unknowns. A rate for extra organics, rock, or import, so an overrun can be priced without a fight.
- Exclusions. Stated plainly, so the lender knows what the budget does not cover.
- Registration and insurance. Many lenders ask for the contractor's registration and a certificate of insurance. Our post on checking an Alaska contractor license shows how to verify both.
- A schedule. When each stage starts and finishes, so it can be matched to the draws.
A single line that says "site work" is hard for anyone to review, lender included.
Where site work lands in the draw schedule
This is a typical order. Your lender may group items differently.
| Stage | Site work in it | What gets checked |
|---|---|---|
| Early draw | Clearing, driveway to a working surface, building pad, foundation excavation | Footing inspection after the excavation is done and before the pour |
| Foundation draw | Foundation drainage and backfill | Foundation inspection, which covers drainage, elevation, and backfill |
| Mid-project | Septic, well line, power and gas trenches | Septic approval paperwork; utility inspections |
| Final draw | Final grade, topsoil, driveway surface | Final inspection and completion report |
Notice the timing problem. Draws are usually released after a stage is done, but your excavator has to mobilize, clear, and haul gravel before the first draw is released. Ask your lender how the first stage gets paid: from your own funds, a deposit at closing, or the first draw. A modest deposit to mobilize is normal, as our estimate guide explains.
Lien releases also come up at each draw. Under AS 34.35, contractors, suppliers, and equipment providers can hold lien rights on your property, and the state's homeowner guide says to get a completed lien release before final payment. Many lenders want one with each draw.
The appraisal and the land you already own
The lender appraises the house as it will be when finished, lot included. Under Fannie Mae's single-closing rules, if you already own the lot, the loan is treated as a limited cash-out refinance, you must hold title before the first construction advance, and the loan-to-value ratio is the loan amount divided by the "as completed" value of the lot and the house. On a purchase, the value side is the lower of the purchase price (lot price plus construction cost) or the as-completed value.
In plain numbers, with made-up figures: if the as-completed appraisal is $500,000 and the loan is $400,000, the loan-to-value is 400,000 divided by 500,000, or 80 percent. A lot you own outright is part of that $500,000. Other loan programs, including portfolio and credit union loans, set their own rules, so ask.
The appraisal's effective date can be no more than four months before the note date under those rules, and a completion report is required at the end.
Contingency: why site work needs one
Site work has more unknowns than any other part of the house. Organics may run deeper than the test holes showed. Rock or water may show up. The fix is unit prices plus a contingency.
Here is how an overrun works. Say the bid carries 400 cubic yards of imported fill at a set unit price, and the organics come out deeper than expected, so the pad takes 600 yards. That is 200 extra yards, or 50 percent more than the bid quantity, and the import line grows by 50 percent. With the unit price already agreed, the math is simple. Without a contingency, that money comes out of your pocket mid-job. Your lender sets the size of the contingency.
AHFC loans and inspection requirements
Alaska Housing Finance Corporation buys home loans made by participating lenders, so you apply through a bank or credit union. Under AS 18.56.300, homes built on or after July 1, 1992 must go through an approved inspection process to be eligible for AHFC financing.
AHFC's New Construction Inspection Guidelines require at least five inspections by an authorized inspector: plan approval, footings, foundation, framing, and final. The inspector cannot be connected to the builder or owner and records the results on Form PUR-102. Three of them touch the dirt work directly:
- Plan approval should be done before construction starts, and AHFC counts construction as started when pilings, footings, or foundation work begins.
- The footing inspection happens after the footing excavation is finished and any reinforcing steel is tied.
- The foundation inspection covers reinforcement, depth, drainage, anchorage, elevation, backfill, and waterproofing. Do not backfill until it is done.
In a city with an AHFC-approved building department, a Certificate of Occupancy replaces the PUR-102. The 2020 guidelines list the City of Kenai, Soldotna, and Seward on the peninsula. Homer and the areas outside cities, such as Sterling and Nikiski, are not on that list, so they use an authorized inspector. Check the current list at ahfc.us.
AHFC's February 2026 notice describes a $10,000 New Home Construction Rebate for owner-occupied new homes. The foundation must be completed and inspected on or after January 2, 2025, the home must rate at least 5-Star Plus, and construction must finish within 18 months of applying. It is first come, first served until funds run out, so confirm it is still open.
Get a bid your lender can use
MNA Construction writes site work bids with line items, quantities, unit prices, and exclusions, laid out so a lender can match them to a draw schedule. We handle site preparation and foundation excavation and schedule around your inspector. Request a free estimate and tell us who your lender is.
Common questions
- Does a construction loan cover land clearing and excavation?
- Usually, yes. Site work is part of the total construction cost, and most construction loans fund it through the early draws. The lender will want it itemized in the contractor's bid, so confirm with your lender how they treat site work and the first payment to the excavator.
- Can land I already own count toward a construction loan?
- Often it does. Under Fannie Mae's single-closing rules, the loan-to-value ratio uses the as-completed value of the lot and house, so an owned lot adds to the value side. Each lender and loan program has its own rules, so ask yours how your land is counted.
- What inspections does AHFC require on a new home?
- At least five: plan approval, footings, foundation, framing, and final, done by an authorized inspector and recorded on Form PUR-102. In cities with an AHFC-approved building department, a Certificate of Occupancy takes the place of the PUR-102.
- Who pays the excavator before the first construction draw?
- That depends on the lender. Some fund a deposit at closing, some expect the owner to cover the first stage, and some release the first draw quickly once early work is checked. Settle this with your lender and your contractor before work starts.