Pond construction in Alaska starts with water and permits, before any digging. On the Kenai Peninsula, a dug pond usually fills from groundwater, so the water table decides where the pond goes and how deep it has to be. If the pond sits in wetlands, connects to a salmon stream, or needs an earth dam, federal, state, and borough permits can apply before the first bucket.

A pond is also a big pile of dirt. A modest pond produces thousands of cubic yards of spoils, and the borough landfill does not take soil. Plan the water, the permits, and the spoils together.

Groundwater-fed or lined

There are two kinds of dug ponds. One fills from groundwater seeping in through sand and gravel. The other holds runoff or pumped water in a basin that does not leak.

The USDA's pond handbook (Agriculture Handbook 590, Ponds: Planning, Design, Construction) says groundwater-fed ponds work only in flat or nearly flat ground, ideally where the permanent water table is within a few feet of the surface. It also says the distance from the normal water level to the ground surface should generally not exceed 6 feet, because every foot of dry dirt above the water costs money to dig and adds nothing to the pond.

FactorGroundwater-fedLined or sealed
Water sourceWater table in sand and gravelRunoff, a well, or roof water
Where it worksLow, flat ground with a shallow water tableAlmost anywhere with a water supply
Water levelRises and falls with the water tableHolds if the liner holds
Main costDigging below the water and handling wet spoilsLiner material and its protection layer
Main riskA summer water table lower than you saw in springLeaks, and liners damaged by ice or roots

Western Kenai soils are often silt over very gravelly sand. That gravel is what feeds a groundwater pond. It is also why a runoff pond in the same soil drains away. The handbook says to avoid porous sites for runoff ponds unless you are prepared to pay for a liner. Dig test holes before design, and check them again in a dry stretch of summer, so a temporary spring water table does not mislead you.

Wetlands and the Army Corps

The ground where a groundwater pond works best, low and flat with water near the surface, is often wetland. Placing dredged or fill material in wetlands takes a Section 404 permit from the Army Corps of Engineers, and side-casting the pond spoils onto wet ground counts.

Federal rules exempt building farm or stock ponds, but that exemption is lost when the work converts wetlands or waters to a use they were not previously subject to and impairs flow or shrinks their reach. A recreational pond dug in wetlands is a poor bet for the exemption. Ask the Corps before you dig. The Corps' Kenai field office is at 805 Frontage Road, Suite 200C in Kenai, phone 907-283-3519. Our post on checking a lot for wetlands covers the screening steps and the timeline.

Salmon water: ADF&G and the borough

If the pond would connect to a stream or lake by an inlet, an outlet, or a ditch, check the water first. Under AS 16.05.871, work that affects the flow or bed of a cataloged anadromous water needs prior approval from the Alaska Department of Fish and Game. Waters count if they are listed in the Anadromous Waters Catalog, which lists almost 20,000 streams, rivers, and lakes statewide. A separate statute, AS 16.05.841, covers fish passage in all fish-bearing waters, cataloged or not.

The borough adds two layers. Its habitat protection rules apply a 50 foot setback from the salmon waters on the borough's list (see our post on the 50 foot setback). Excavation in a mapped floodplain needs a borough floodplain permit. The Kenai River Center handles the borough permits and coordinates with the state and federal agencies in one place; our post on the Kenai River Center permit walks through it.

A pond with no connection to any stream, dug in upland ground outside the setback and floodplain, avoids most of this. That is the easiest pond to permit.

Building an embankment: Alaska dam safety

Building up an earth berm to hold water changes the job. Under AS 46.17.900, as the Department of Natural Resources dam safety fact sheet explains, a barrier is a regulated dam if it meets any one of these:

  • It impounds 50 acre-feet or more and is at least 10 feet high
  • It is 20 feet high or more
  • Its failure would threaten lives and property

A regulated dam needs a Certificate of Approval to Construct before any work, based on plans from a qualified civil engineer. DNR typically asks for 180 days of review. Then the dam needs a certificate to operate and periodic safety inspections.

For scale, 50 acre-feet is about 2.18 million cubic feet, or roughly 16 million gallons. Most backyard ponds hold a small fraction of that. The third test is the one to watch: a small berm above a road, a driveway, or a neighbor's house can still threaten property if it fails. If your design holds water above the surrounding ground, call the DNR Dam Safety and Construction Unit at 907-269-8636 early.

Dig math, spoils, and safety slopes

The pond handbook estimates volume with the prismoidal formula: top area plus 4 times the middle area plus the bottom area, times depth, divided by 6, divided by 27 for cubic yards. Its own example is a pond 100 by 40 feet at the bottom and 12 feet deep, with 2 to 1 side slopes and a 4 to 1 ramp at one end.

ItemResult
ExcavationAbout 3,996 cubic yards
Water stored, full to the ground surfaceAbout 2.48 acre-feet, or about 807,000 gallons
Loose volume to move, at a 25 percent allowanceAbout 5,000 loose cubic yards
Truckloads if hauled at 10 yards per loadAbout 500 loads

That is why spoils planning comes first. The borough's Central Peninsula Landfill does not accept dirt or soil without a special waste permit, so most pond spoils stay on site. The handbook's guidance: place spoils so their weight does not destabilize the pond banks and rain does not wash them back in, keep stacked slopes no steeper than the soil's natural angle of repose, and shape them to blend in. Clean gravel from a pond is useful for driveways or pads. Peat and silt are good only for landscaping berms. None of it goes onto wetlands without a permit.

Slopes are also a safety question. The handbook says side slopes are generally 1 to 1 or flatter to keep banks from sloughing, and it tells contractors to eliminate sudden drop-offs and deep holes and remove stumps and debris. Our recommendation for a pond near a house: lay at least part of the shoreline back much flatter, or build a shallow shelf, so a child or a dog that slips in can walk out. Ice thickness varies across a pond, so post warnings and keep a ring buoy or a long pole at the shore.

Stocking the pond with fish

Putting live fish in a pond takes a permit. Under 5 AAC 41.005, no one may collect, transport, possess, or release a live aquatic organism into the waters of the state without a fish transport permit from ADF&G. The department's application instructions call for a separate permit for each species, stock, and release location, and they ask whether the release site is landlocked, meaning it has no flowing outlet.

Two practical points. A pond with an outlet to a stream is a harder case, because stocked fish can leave. And moving fish from a nearby lake into your pond yourself is exactly what the rule prohibits without a permit. Applications go to the ADF&G permit coordinator in Juneau, (907) 465-4724.

MNA Construction digs ponds across the Kenai Peninsula with test holes first, a plan for the spoils, and slopes built for the way the pond will be used. See our excavation and earthwork service, then request a free estimate with your lot location and what you want the pond for, and we will look at the water and the permits with you before we price the digging.

Common questions

Do I need a permit to dig a pond in Alaska?
Often not, if the pond is in upland ground, away from salmon water and the floodplain, with no dam. A pond in wetlands usually needs an Army Corps permit, one that connects to cataloged salmon water needs ADF&G approval, and a berm that meets the state dam definition needs a DNR certificate. On the Kenai, the borough's habitat and floodplain rules also apply near water.
How much does it cost to dig a pond?
Bob Vila's national cost guide lists pond digging at $60 to $200 per cubic yard, or $55 to $150 per hour for larger ponds. Those are national figures, not Alaska prices. Your cost depends on the yardage, whether you dig below water, and whether spoils stay on site.
Can I put fish in my pond in Alaska?
Only with a fish transport permit from the Alaska Department of Fish and Game. The state's rule covers collecting, transporting, possessing, and releasing live fish, and a separate permit is needed for each species, stock, and release location. Apply well before you plan to stock.
Will a pond dug in gravel hold water?
It will hold water only if it reaches the water table, and then its level rises and falls with the groundwater. A pond in gravel above the water table drains unless it has a liner. Test holes checked in a dry stretch of summer tell you which one you have.