Demolition

Contaminated Soil Removal in Alaska: Fuel Spills and ADEC

MNA Construction··6 min read

Contaminated soil removal in Alaska is a regulated cleanup, not a dirt job. A fuel spill gets reported to ADEC, a qualified environmental professional sets the cleanup plan and takes the samples, and state rules require ADEC approval before contaminated soil is moved off the site or disposed of. The excavation contractor digs, stockpiles, loads, and backfills to that plan.

Most fuel-contaminated soil on the Kenai Peninsula comes from heating oil tanks and lines, with gasoline from vehicles, equipment, and old fuel tanks behind it. Here is who does what, how the cleanup levels work, and what the job looks like once the machine shows up.

When a fuel spill has to be reported

Alaska's reporting thresholds are in 18 AAC 75.300.

Where the oil wentWhen to report
Any amount to waterImmediately
More than 55 gallons to landImmediately
More than 10 and up to 55 gallons to landWithin 48 hours
1 to 10 gallons to landIn a written record sent to ADEC monthly

With a buried tank, nobody knows how much leaked. Report it. During business hours, call ADEC's Central Alaska Response Team at (907) 269-3063. After hours, call 1-800-478-9300.

One exception changes the path. A release from a regulated underground storage tank, such as a buried tank at a business that fuels vehicles or equipment, falls under the separate UST rules in 18 AAC 78 instead. A tank that only heats the building on the property is not a regulated UST.

Who does what in contaminated soil removal

The state rule at 18 AAC 75.333 says a qualified environmental professional, usually an environmental consultant, prepares the site characterization work plan and report, collects the samples, and supervises the cleanup. The rule requires that person to be an impartial third party.

WhoWhat they do
Owner (the responsible person)Reports the spill, hires the consultant, pays for cleanup, keeps ADEC informed
Environmental consultantWrites the work plan, samples soil and water, decides how far to dig, reports to ADEC
ADECReviews the plan, approves moving and disposing of soil, decides when the case can close
Excavation contractorDigs where the consultant says, builds the stockpile, loads trucks, backfills and compacts
Disposal or treatment facilityAccepts the soil once ADEC and the facility approve it

Do not let anyone, including us, guess how far the contamination goes. The consultant's samples decide where the digging stops.

How cleanup levels work

The cleanup numbers live in the tables of 18 AAC 75.341. You do not need to read them, but you should know how they are built, because they decide how much soil comes out.

  • Method one is a scoring method for petroleum. Table A1 sets levels for sites outside the Arctic, based on things like depth to groundwater, rainfall, soil type, nearby water, and how much soil is contaminated.
  • Method two uses fixed tables. Table B2 covers petroleum hydrocarbons, and Table B1 covers other chemicals, including the ones in gasoline such as benzene.
  • Fuel ranges. Lab results for petroleum come back in ranges: gasoline range organics (GRO), diesel range organics (DRO), and residual range organics (RRO). Heating oil shows up mostly as diesel range.
  • Climate zones. The tables have separate columns for sites with under 40 inches of yearly precipitation and sites with 40 inches or more. Homer, at about 24 inches a year, falls in the drier column. Seward, at about 70 inches, falls in the wetter one. Your consultant confirms the figure for your site.
  • Exposure. Levels are set by how people could be exposed, through touching or swallowing soil, breathing vapors, or contamination reaching groundwater.

Your consultant picks the method and the levels for your site and explains them to ADEC.

Digging it out: the stockpile rules

The handling rules in 18 AAC 75.370 are where the excavation contractor's work is regulated. In plain terms:

  1. Do not blend contaminated soil with clean soil to bring the numbers down, unless ADEC approves it.
  2. Keep contaminated soil separate by contaminant and by where it is going.
  3. Set petroleum-contaminated soil on a liner that meets the rule's specifications, or on another impermeable surface.
  4. Cover the pile with reinforced polyethylene at least 6 mils thick, lapped over the bottom liner.
  5. Keep the pile at least 100 feet from surface water and private water supplies, and at least 200 feet from a well serving a community or similar public water system.
  6. Inspect the cover regularly and contain any leachate (liquid draining out of the pile).
  7. Get ADEC approval before moving or disposing of the soil.

Rule 18 AAC 75.325(i) says the same thing from the other side: a responsible person has to get approval before disposing of soil from a site under the cleanup rules. Hauling contaminated soil to a gravel pit, a low spot, or a neighbor's lot is not an option.

Where contaminated soil can go on the Kenai

There are only a few legal destinations, and each needs approval first.

  • Thermal treatment. In November 2021, ADEC approved an operations plan, with conditions, for a soil treatment facility run by Soil Treatment Technologies on the Kenai Spur Highway in Nikiski, the Peninsula Clarion reported. The process heats petroleum-contaminated soil to drive off the fuel, then treats the gases. ADEC approves each load sent there. Ask your consultant whether it is operating and taking soil.
  • Borough landfill as special waste. The Central Peninsula Landfill does not take soil without approval. Contaminated soil goes through the borough's special waste policy, with lab results, and the fee schedule lists special waste at $135 per ton with a one-ton minimum.
  • Treatment on site. Some sites treat soil in place or in a lined cell on the property. That takes an ADEC-approved plan and time.

Your consultant and ADEC decide which one fits. Call KPB Solid Waste at (907) 262-9667 early if the landfill is the likely destination.

A worked example of the dig

Here is the math for a buried heating oil tank leak where the consultant's samples outline a pit 15 feet by 15 feet by 6 feet deep.

  1. Volume. 15 x 15 x 6 is 1,350 cubic feet. Divide by 27 for 50 cubic yards as it sits in the ground.
  2. Weight. Assume about 1.5 tons per cubic yard for this example. That is roughly 75 tons. The scale ticket decides the real number.
  3. Disposal at the special waste rate. 75 tons x $135 is about $10,125, before trucking, lab work, and the consultant.
  4. Backfill. The hole takes 50 cubic yards of compacted clean fill, which means more than 50 loose yards delivered.

Every extra foot of depth across that footprint adds about 8 cubic yards and 12 tons. That is why the consultant's confirmation samples, taken from the walls and floor of the hole, matter so much.

Help paying for a heating oil spill

ADEC launched a home heating oil spill cleanup program in January 2026, funded by a one-time $450,000 appropriation. The Peninsula Clarion reported that it offers $13,000 to $17,000 per eligible homeowner, depending on location, and covers cleanup materials, excavation, and cleanup of contaminated soil. Some older spills may qualify if soil disposal and transport are needed to close the case.

Do the arithmetic: $450,000 at $13,000 to $17,000 per home covers roughly 26 to 34 cleanups statewide. Apply early, and check homeheatingoiltanks.alaska.gov for current eligibility and whether money remains.

MNA Construction does the excavation side of fuel cleanups across the Kenai Peninsula, including Nikiski and Soldotna: tank pulls, digging to the consultant's limits, lined stockpiles, loading for approved disposal, and clean compacted backfill. See our demolition and tank removal work, and read our guides to heating oil tank removal and clean fill. Send us your consultant's work plan through our estimate request and we will price the dig.

Common questions

Who pays to clean up contaminated soil in Alaska?
The responsible person does, which is usually the owner or operator of the tank or property where the spill happened. A state program launched in 2026 offers $13,000 to $17,000 toward eligible home heating oil spill cleanups while its funds last. Homeowners insurance coverage for fuel leaks varies, so ask your agent.
Can I dig up fuel-stained soil and spread it out to air dry?
No. State rules require ADEC approval before contaminated soil is moved or disposed of, and they prohibit blending it with clean soil without approval. Spreading it on your property can make the cleanup larger. Report the spill and let a qualified environmental professional set the plan.
How do I know if the soil around my oil tank is contaminated?
A fuel smell, dark staining, or an oily sheen on water in the hole are strong signs, but only lab samples tell you how much and how far. A qualified environmental professional collects the samples and compares the results to ADEC's cleanup levels. If you see signs during a tank pull, stop digging and report it.
Can contaminated soil be cleaned instead of landfilled?
Yes, in some cases. Petroleum-contaminated soil can be treated by heating it at a thermal treatment facility, or treated on site under an ADEC-approved plan. ADEC approved a thermal treatment facility in Nikiski in 2021. Your consultant and ADEC decide which option fits your site.

Planning excavation or site work in Southcentral Alaska?

MNA Construction is owner-operated and ready to help. Let's talk about your project.