Costs

Concrete Removal Cost in Alaska: Slabs, Driveways, Footings

MNA Construction··5 min read

Concrete removal cost in Alaska comes down to how many tons of concrete you have, how long it takes to break and load, and the disposal fee at the end. Normal concrete weighs about 140 to 150 pounds per cubic foot, so a 4-inch two-car driveway measuring 24 by 30 feet is roughly 17 tons. At the Kenai Peninsula Borough's $90 per ton rate, that is about $1,570 in tipping fees alone, before machine time, trucking, and putting the ground back.

MNA does not publish a concrete removal price list, because access, thickness, and steel change every job. What we can do is show you the math, so you can size your own job and read a bid with a sharper eye.

What drives concrete removal cost in Alaska

Cost driverLower costHigher cost
Thickness4-inch patio or walk6-inch shop slab or thickened edges
ReinforcementNone, or light wire meshRebar grid, footings with heavy steel
AccessMachine drives right onto itBehind a fence, under eaves, next to a septic tank
Partial removalWhole slab comes outSaw cut needed to save the rest
HaulShort run to the landfillLong haul, or spring load limits on the roads
DisposalClean concrete reused on siteEvery ton hauled and paid for at the scale
What comes afterLeave it rough gradedGravel, topsoil, seed, or a new driveway section

Disposal is the one number you can calculate yourself, and it scales directly with weight.

The weight math for a slab, driveway, or footing

Iowa DOT's concrete testing method puts normal weight concrete at 140 to 150 pounds per cubic foot. A cubic yard is 27 cubic feet, so a cubic yard of concrete weighs about 3,780 to 4,050 pounds, or roughly 2 tons. Here is the method, using 145 pounds as the middle:

  1. Multiply length by width by thickness, all in feet, to get cubic feet. Four inches is 0.333 feet and 6 inches is 0.5 feet.
  2. Divide by 27 for cubic yards.
  3. Multiply cubic feet by 145 for pounds, then divide by 2,000 for tons.
  4. Multiply tons by $90 for the borough tipping fee.
JobSizeCubic yardsTonsTipping fee at $90
Patio12 x 16 ft, 4 in thick2.44.6about $420
Two-car driveway24 x 30 ft, 4 in thick8.917.4about $1,570
Shop slab30 x 40 ft, 6 in thick22.243.5about $3,920
Footing only140 ft long, 16 in wide, 8 in deep4.69.0about $810

The driveway works out like this: 24 x 30 x 0.333 is 240 cubic feet, which is 8.9 cubic yards. At 145 pounds, 240 cubic feet is 34,800 pounds, or 17.4 tons. At the low and high ends of the weight range it is 16.8 to 18 tons.

For a whole foundation with stem walls or a basement, our house demolition cost guide runs that math.

Broken concrete takes up much more room in a truck than it did as a slab. A dump truck usually hits its weight limit before the box looks full, so ask any bidder how many loads they expect.

Rebar, mesh, and how the concrete comes out

Many residential slabs have welded wire mesh, and footings and heavier slabs often have rebar. Steel holds broken pieces together, so the operator has to break smaller and pull the pieces apart. That is the main reason a reinforced slab takes longer than a plain one the same size.

Two tools do most of the work:

  • Excavator bucket. On a thin, cracked, unreinforced slab, an operator can often pry under the edge and lift pieces straight into the truck.
  • Hydraulic breaker. A breaker, also called a hammer, mounts on the excavator in place of the bucket. Thick or reinforced concrete gets broken first, then loaded.

When part of the concrete stays, such as a garage slab next to a driveway coming out, a saw cut makes a clean line so the breaker does not crack what you are keeping. If you are digging below the old slab for a new footing or line, call Alaska Digline at least two working days ahead. Locates are free, and they apply to private projects too.

Disposal options on the Kenai Peninsula

The borough's construction and demolition cell takes masonry, which its locations page lists as brick, concrete, rock, and stone. The cell is at the Central Peninsula Landfill at Mile 98.5 of the Sterling Highway in Soldotna, and at the Homer and Seward facilities.

  • Rate. The borough fee schedule lists inert waste, which includes construction materials, at $90 per ton with a $20 minimum at sites with scales.
  • Sites without scales. Charges go by volume, such as $90 for 2 to 5 cubic yards and $180 for 6 to 10.
  • Who pays. Commercial haulers pay by the ton. Residents are charged only for a short list of items, so a homeowner hauling their own load may be treated differently. Call (907) 262-9423 to confirm before you count on it.
  • Clean loads. The Central Peninsula Landfill does not accept dirt or soil, so knock the dirt off before you haul. Separated steel goes to the metals pile.
  • Limits and hours. Homer and Seward cap commercial construction debris at 250 cubic yards per job. At Soldotna, the back areas close at 5:30 p.m., and loads that cannot be finished by then are turned away.

Reusing it on site is the other option. Alaska's solid waste rules, at 18 AAC 60.005(c)(3), exempt bricks, mortar, and Portland cement concrete, including reinforcing steel that cannot be easily removed. The exemption does not apply if the concrete is mixed with other waste, or if it creates a nuisance or a threat to health or the environment. Asphalt is not on that list.

Buried slab chunks leave gaps that settle, so keep them out from under footings, slabs, driveway sections, and drainfields. Wetlands and the 50-foot salmon stream setback have their own permit rules. A low spot in the back of the lot, under a thick cap of soil, is the usual place. Check any city or subdivision rules before you bury anything.

Putting the ground back after concrete removal

Taking out a slab leaves a shallow hole, plus whatever gravel base sits under it. What goes back depends on what is next:

  • Lawn. Four inches of topsoil over the 24 by 30 foot driveway footprint is 240 cubic feet, or about 8.9 cubic yards, before settling. See our topsoil and seeding post.
  • New driveway or pad. The old base may be reusable if it is clean. A new gravel section goes on top once the subgrade is firm.
  • Building. Fill under a new structure has to be compacted structural material. Our post on fill dirt vs structural fill explains the difference.

Either way, grade the finished surface so water runs away from the house.

Get a concrete removal estimate

MNA Construction does demolition and concrete removal across the Kenai Peninsula, from Soldotna to Homer, including breaking, loading, hauling, and regrading the site for what comes next. We are licensed and insured, and estimates are free. Send us the size, thickness, and a few photos, and tell us whether the concrete has rebar.

Common questions

How much does a cubic yard of concrete weigh?
At 140 to 150 pounds per cubic foot for normal weight concrete, a cubic yard weighs about 3,780 to 4,050 pounds, or roughly 2 tons. That weight is more than many pickups are rated to carry in one load.
Does the Soldotna landfill take concrete?
Yes. The Central Peninsula Landfill takes concrete in its construction and demolition cell, and the borough lists inert waste at $90 per ton with a $20 minimum for loads that pay by weight. Keep dirt out of the load, since the landfill does not accept soil. Call (907) 262-9423 to confirm current rates.
Can I bury old concrete on my property in Alaska?
State solid waste rules exempt clean Portland cement concrete, including rebar that cannot easily be removed, as long as it is not mixed with other waste or causing a nuisance. Keep it out of wetlands, the 50-foot salmon stream setback, and anywhere you will build, drive, or put a drainfield. Check city or subdivision rules first.
Is a slab with rebar more expensive to remove?
Usually, yes. Steel holds the broken pieces together, so the slab has to be broken smaller with a hydraulic breaker and the pieces pulled apart before loading. The tonnage and tipping fee stay about the same, but machine time goes up.

Planning excavation or site work in Southcentral Alaska?

MNA Construction is owner-operated and ready to help. Let's talk about your project.

Get a Free Quote